Executive Summary
A global specialty chemicals and Oil & Gas major needed to launch an ultra-high-purity Isopropyl Alcohol (IPA) product for the electronics intermediates market in the US- inside an operating brownfield site, on a fixed window, with a business case that would set the benchmark for future expansions.
LTTS engineered the program end-to-end - Pre-FEED, FEED, detail design, and procurement - delivering ~ 10 Mn in CAPEX savings through value engineering and India sourcing, in just 24-months.
Read the Full Case Study. Anytime, Anywhere
Download Case StudyClient Challenge
The client was chasing a fast-closing market window: ultra-high-purity IPA is a critical intermediate for the electronics industry, and demand was rising faster than qualified capacity. Missing the window didn’t just mean lost revenue - it meant ceding a competitive position in a segment where qualification cycles with downstream electronics customers can take years to re-open. The obvious fix - a clean greenfield build on a new plot - was off the table: it would have added land, permits, and utility-tie-in time that the business case could not absorb, and it would have stranded the client’s existing brownfield infrastructure and workforce. What they actually needed was a greenfield-grade facility built inside a live, congested brownfield, with a repeatable execution template that could be cloned for the next expansion if the economics held.
Engineering Complexity
The complexity here wasn’t in any single problem - it was in four compounding challenges that had to be solved at the same time, on the same plot, against the same clock.
Greenfield inside a live brownfield.
The plot sat inside an operating “dirty” facility. That meant underground unknowns (legacy piping, foundations, cables), constrained heavy-lift paths for two 220+ ft columns and three pipe-rack/staging modules, and hot-tap/turndown tie-ins that had to be engineered without shutting the host plant.
Pilot-to-commercial jump
The engineering had to move directly from pilot-plant data to full commercial scale, without an intermediate field-proven baseline to anchor the design against.
Long-lead procurement on a fixed window
30+ pieces of long-lead, heavy equipment had to be sourced, shipped, dressed-up on site, installed, and commissioned inside a 24-month envelope - one slipped forging pushes the whole critical path.
Thermosyphon reboiler at column height
At ~220+ ft columns, thermosyphon hydraulics leave no margin -driving force, vapour disengagement, and turndown all must balance at once, or the column stalls off-design.